The Trouble With Energy - Part 3.

This is part 3 of a series of posts co-authored by phoenix, who is an Engineer heavily involved in the energy sector. It will be based on a submission we made recently to the Australian Government.

Part 1 is here.

Part 2 is here.

Introduction

In part 2 we introduced a model for looking at energy use over the next few decades and applied it to the Australian situation. This model:

  • Estimates how much time will be needed to achieve a transition to alternate and renewable energy sources.
  • Estimates how much energy will be needed to achieve this.
  • Estimates the cost of this transition.
  • Calculates (based on industry figures) how much energy we have left in our remaining energy reserves and how long this will last.

The model shows that:

  • If Business As Usual is the assumed paradigm, the energy required may exceed the energy available.
  • If Business As Usual is the assumed paradigm, the cost of the transition is likely to place an untenable strain on GDP.

The market can be counted on to deal with this problem, but over the last few months we have seen that the market can be brutal. BAU is not an option. Our choice is to manage the problem, or let the market manage it for us.

There is a gap between our current expectations and the reality we will experience over the next few decades. In developing this model we are quantifying that gap. This allows decisions to be made based on hard numbers.

In this post we apply the model to the larger picture.

World Situation

Following on from the analysis of Australia’s energy security the following broad analysis has been performed to ascertain the relationship between remaining fossil fuel energy and the capacity to put in place an equivalent economy based of renewable energy.

The basis for this analysis is the presumption of a Business As Usual (BAU) transition from an economy based on fossil fuels to an economy based on renewable energy.  Although we assume BAU for the purposes of vthis post, the authors are not advocating BAU. This analysis clearly demonstrates that a BAU future is simple not possible. Although we demonstrate that BAU is not possible, this does not indicate that we believe that an alternate infrastructure cannot be achieved. It merely shows that the requirements associated with a building an alternate energy structure are not compatible with the profligate lifestyle associated with BAU.

How Much Time Do We Have?

As discussed in the previous post, most production vs. resource figures are established by assuming a continuation of the current demand or extraction rate.  While this may be a reasonable methodology for determination of the life of a mine or the value of the resource it is patently false for determination of our overall resource security. Demand rates for all of our energy resources are climbing year by year. 

The paradigm of continually increasing growth driven by an increasing population and an expectation of improving standards of living demands a continuing increase in production of our natural resources. The following table shows the World’s major non renewable energy resources together with their expected life calculated on this basis.

Coal Oil(inc all liquids) Gas Uranium
Unit Billion Tonnes Billion Barrels Trillion M3 ThousandTonnes
Base Year 2007 2007 2007 2007
Resource 847 1,238 177 5,469
Consumption 6.4 27 2.3 65
Growth Rate 2.95% 1.39% 2.1% 1.2%
Life Expected 63 years 32 years 41 years 59 years
Resource Exhausted 2070 2039 2048 2066

Sources:          BP World Energy

Note 1: All of the above numbers including growth rates have been established from  the industry-recognised source listed above.  Long term growth rates have been used based on growth from 1998 to 2007.

Note 2: This is a simplistic analysis, assuming an exponential increase up to a precipitous fall.  Of course this will not occur.  Each of the fuels will undergo their own peaking curve.  In order to generate the most conservative possible result, we have not taken this into account, nor have we considered the resulting cost increases that will occur when the supply and demand curves separate for these basics energy commodities.

Of course there will be continual additions to the current proven reserves that will have the potential to extend the above calculated life expectancies.  On the other hand there are a number of factors that will tend to decrease available life expectancies:

  • The exponential effects of EROEI will dramatically increase energy demand as we approach exhaustion of the energy resources.
  • Higher energy demands will also result from higher extraction (or recycling) costs associated with the whole range of other economy related resources.
  • The figures quoted above do not take into account any restriction in fuel availability as a result of greenhouse gas limitations.
  • As depletion occurs in some of the above resources it is likely that alternative fossil fuels will be transmuted to fill the required shortfall eg. coal to oil, gas to oil, etc.  These transfers of energy almost always result in lower overall energy efficiencies.

On balance then the above figures represent a reasonable view of the expected life of our non-renewable energy resources in a business as usual scenario.  The above life expectancies can then be averaged based on energy values.

We have until around 2052 to put in place renewable technologies to provide for our energy needs.

The size of the task

In order to establish the time required to put in place renewable sources for energy supply, it is necessary to make assumptions with regard to the infrastructure that needs to be constructed. This is a very difficult task given that much of the technology is in a developmental phase.  Picking winners is not easy and frequently not wise. However by taking an average developmental cost for a range of possible technologies,we can be fairly confident about the expected implementation effort and time required. 

The following table represents one possible scenario in respect of the conversion of demand from fossil based energy to renewables.  The table indicates both a growth in demand up to the year 2050 and the effects in energy efficiency terms of conversion from one form of energy base to an alternate renewable source.

Energy Source Conversion

Energy uses Current     Renewable Conversion
  Source Usage EJ/y Growth Rate Usage 2050 Source Efficiency Gain Usage 2050
(Non- electricity based)              
Agriculture Oil 7 1.2% 11 Biofuels -33% 15
Industry/Commerce Oil 18 2.5% 50 Electricity 10% 45
  Gas 34 2.5% 94 Electricity 10% 85
Road Transport Personal Oil 58 0.0% 58 Electricity 70% 17
Freight (Road/Rail/Sea) Oil 39 2.5% 107 Biofuels -33% 71
          Electricity 60% 21
Public Transport Oil 7 7.0% 110 Electricity 70% 33
Air Transport Oil 15 0.0% 15 Biofuels -33% 20
Products Oil 24 2.5% 65 Biofuels -33% 86
Heating Oil 14 1.2% 22 Electricity 60% 9
  Gas 26 1.2% 43 Electricity 60% 17
Metal smelting Coal 19 2.5% 53 Electricity 20% 43
               
Electrical demand   72 2.5% 198 Electricity 0% 198
               
Sub-total Electricity             270
Sub-total Biofuels             192
Total   333   827     661

Notes

1/ The basis of GDP growth has been assumed be a  2.5% p.a..  This value is in line with the relatively modest world GDP growth posted in 2008 - lower than 2007, but higher than the projected figure for 2009.  The authors believe that even this low level of growth will be difficult to achieve, given the energy constraints that will be place on the world economies.

2/ In line with other analysis described in this paper the energy demand forecast has been kept in direct proportion to the projected GDP figures for all industry and commercial based energy uses.

3/ Population related energy uses have been kept in line with the world’s current 1.2% p.a. population increase rate.

4/ The classification of energy use into sectors has been a very difficult exercise and represents an amalgam of numerous published data sets.  If readers have any better definitive data that provides energy use by source and sector the authors would appreciate any input.

4/ In anticipation of a dramatic
increases in energy pricing, the growth figures for personal transport have been forecast at 0%.  As a complimentary allowance the growth in public transport has been increased to 7%.  The balance between these growth numbers represents a reasonable transference of energy use between these two categories.

5/ Again in anticipation of the effects of high energy costs the level of air transport growth has been limited to 0%.

6/ The efficiency gain nominated for all conversions from oil based fuel to biofuels is a loss of 33%.  This represents a nominal loss due to EROEI effects.  It assumes an EROEI for future biofuels of around 3.   Given the current analysis from the USA on ethanol based biofuels this is very optimistic assumption.

7/ The conversion efficiency for most oil to electricity conversions has been assumed to be 70%.  This figure represents a combination of a number of factors including:

  • Change in mechanical efficiency between electric and internal combustion engine drives
  • Losses due to transmission and storage of electricity
  • Reduction in vehicle weights due to energy cost drivers

8/ No currently viable technology exists for large scale smelting of iron ore using renewable energy sources.  The figures for energy efficiency therefore represent a nominal allowance that this technology when developed will be based on electrically derived heat.

Therefore under this scenario to completely replace the world's energy sources with renewables will require the construction of the appropriate infrastructure to produce:
  • 270 EJ or 75,092 TWHr of electricity and
  • 192 EJ or approximately 5,800 gigalitres of biodiesel

The cost of the task

With respect to the electrical demand, our future energy requirements will undoubtedly come from a range of renewable sources. These will include hydro, wind, biomass, solar thermal and solar PV and geothermal.  The table below indicates a possible mix of sources and their respective capital construction costs.

Renewable Electricity Generation

Source Proportion Generation Utilisation Capacity Capital
Cost
    TWhr/y   GW USD$/kW US$Billion
Hydro 15%         
10,716
70%          
1,748
2500          
4,369
Wind 30%         
21,433
25%          
9,787
1600         
15,658
Biomass 15%         
10,716
70%          
1,748
2000          
3,495
Solar Thermal 20%         
14,288
20%          
8,155
2400         
19,573
Solar PV 10%          
7,144
20%          
4,078
5000         
20,389
Geothermal 10%          
7,144
70%          
1,165
2500          
2,913
             
Plus already built            
3,650
       
Total 100%         
75,092
          
26,680
          
66,397

Notes

1/ Utilisation factors indicated above reflect the relationship between the average working generation capacity and that needed to provide a consistent reliable grid supply. 

2/ Utilisation factors for Solar Thermal and Solar PV are indicative of current technologies in these respective fields with an overlay of system reliability.  A number of proposals exist for extending the daily range of solar thermal.  While these heat storage technologies may enhance the application of solar thermal they will not significantly alter the capital cost per MW delivered.

3/ The utilisation factor attributed to Wind is probably low by current wind farm development standards, which aim for an availability of between 30% and 35%.  This number has been reduced to reflect actual return figures for installed wind generation and to reflect the fact that, in order to achieve the overall output required, wind-farms will need to be developed at locations not currently considered viable.

4/ Utilisation of Hydro, Biomass and Geothermal have been kept low to recognise that these technologies will probably fulfil the role of peaking power plant.

The infrastructure required for provision of biofuels will be a significant challenge, hence the limitation of this fuel source for all uses except where it is irreplaceable because of energy density.  The production of biofuels on the scale required is unprecedented. Production of sugar or grain based ethanol for this volume could not be contemplated.  It appears that the only viable biofuel at this level of production will be production of algal based biodiesel.  Research has indicated that this form of biodiesel production will involve plant capital costs in the region of US$6.5 Million per megalitre of production capacity.  The capital cost of the infrastructure to produce 5,800 GL per year will therefore be approximately US$37,900 Billion.

The total direct cost of revamping the world’s energy production infrastructure will be in the order of US$104 Trillion.

Some points to note in respect to this number.

  • Although the cost has been based on a range of assumptions concerning energy technologies, it is unlikely that a different mix of conversions or replacement technologies would greatly affect the bottom line price.
  • The figure quoted only represents the major energy production plant required.  In parallel with this will be a similar cost associated with the changes made by energy users (i.e. electric vehicles, mining and manufacturing  equipment, rail lines, power transmission, metal smelters etc. etc....)
  • The cost assumes a single transition from the current energy production infrastructure to the final renewable infrastructure.  This won’t happen.  As successive governments are driven by the need to maintain the power on and the fuel tanks full there will be a staged series of interim technologies implemented.  Depending on the quality of vision of political and industry leaders these interim technologies could consume as much or more than the cost indicated for the final conversion.
Given the above considerations it is likely that the total costs associated with transitioning the world to the fully renewable economy will be in the order of US$ 150 Trillion.

What can we afford to spend?

Total world GDP is currently around US$ 70 Trillion per year.  This GDP is growing in real terms at a long term average rate of around 3.5%.  A growth rate of 1.2% is required to maintain a stable GDP per capita.

Looking at the US$150 Trillion required expenditure this represents an expenditure of  US$3.5 Trillion per year over the period up to 2052.  This figure is in turn represents 5% of world GDP for the period.   Now, there are a few savings along the way:

  • The expenditure that would normally be required for the replacement and building of new conventional power plant under a BAU future.  Based on current capacity per capita this works out to be about US$250 Billion per year.
  • There would be a progressive saving on fossil fuel extraction and supply costs.  This would average out at approximately $US700 Billion per year.

The economic drag imposed by the required investment would therefore amount to about  US$ 2.5 Trillion per year on the world economy.  This continuous drag will occur over a period where we also experience the peaking of not only the fossil fuels being replaced but also the common construction materials such as copper, nickel etc.  It is difficult to see how the world economy could cope with such a demand.

Is the world capacity associated with this investment possible ?  The only way we can get a perspective on this is by looking at the construction requirements.  The different power plant types listed in the table above will have a differing construction components ranging from hydro plant involving perhaps 90% construction to solar PV where the construction component may drop as low as 20%..  On average we will assume a construction component of 40% of the investment cost.  This then amounts to US$1.4 Trillion per year.  Over recent years the world has undertaken approximately US$5.5 Trillion in construction work per year.  Of this less than 25% or US$ 1.4 Trillion is attributed to industrial construction of the type used on power plant or petrochemical plant.    So in order to make the transition the entire world capacity for industrial construction would need to be dedicated to the task.  This means no construction of new mines or manufacturing plants or materials processing lants.  This does not seem at all feasible.

Conclusion

It appears that a conventional BAU transition to a completely renewable energy economy is just not possible or at the very least there are serious concerns over the capacity of the world economy to facilitate this transition over the remaining life of our fossil fuel reserves. 

In order to make the transition possible we face a range of possible compromises to BAU:

  • Reduction in energy demand through conservation
  • reduction in energy demand growth through population limitation/reduction
  • continuing the limited access to energy to large portions of the world population
  • breakthroughs in energy conversion efficiency
  • large new resource identification
  • the roll out of renewable energy generation raised to a war footing for all industrialised countries

In part 4 we look at some possible solutions.

The critiques I posted of the last two articles apply again here, since the assumptions and conclusions of those two feed into those of this one. I'm sure others will repeat themselves.

The analysis needs some comparative figures. For example,

  • the cost of getting the same energy entirely from fossil fuels over the time period envisaged for the conversion to renewables
  • the cost in disruptions to economy and society of simply letting the fossil fuels run short and replacing them with nothing

A lack of comparison is the most serious weakness of this paper. For example,

The figure quoted only represents the major energy production plant required. In parallel with this will be a similar cost associated with the changes made by energy users (i.e. electric vehicles, mining and manufacturing equipment, rail lines, power transmission, metal smelters etc. etc....)

You've not given a clear time period for the conversion to renewables. However, it seems fair to assume you're thinking of more than a generation (30 years). Even if coal fell like manna from the heavens and the Earth had a creamy nougat center of oil, over those 30 years much of our vehicles, mining and manufacturing equipment, rail lines, power transmission, metal smelters and the like would be replaced anyway.

So if we have a petrol-burning car now in 2009, and are going to have to replace it in 2020 at the latest, whether we're replacing it with a $10,000 petrol-burning car or a $10,000 electric car doesn't matter economically. It only matters if one is $10,000 and the other $15,000 or $5,000.

Your figures are absolute rather than relative. It's like someone saying to us, "buying your house will cost you $300,000 over 20 years!" Yes, it will. But if we didn't buy the house, we'd have to pay rent anyway, so the question must be what extra cost we have because of our choice.

Just as whether we own or rent, we're not going to let ourselves be homeless over the next 20 years, so too will we as a society not let ourselves be without electricity, transport and so on.

Whatever we do, we're going to spend shitloads of cash on building stuff. The only questions are:

  • what will we build?
  • how much more will it cost than building something else?
  • is it worth it?

Your paper doesn't look at extra costs, only absolute costs. It thus vastly overstates the magnitude of the problem in economic terms. Presumably the aim is to raise the alarm. That's a good thing to do. But when you overstate the problem, people find excuses to dismiss what you say. Between crying wolf! and moderating everything into meaningless bland bureaucratese there's a sensible middle ground where you present the problem and its solutions in a reasonable and fair manner.

This ain't it.

I agree completely. I'm very pleased with how sensible and polite the posts have been on this article! Hopefully it doesn't devolve into namecalling anytime soon =)

Your paper doesn't look at extra costs, only absolute costs. It thus vastly overstates the magnitude of the problem in economic terms.Presumably the aim is to raise the alarm. That's a good thing to do. But when you overstate the problem, people find excuses to dismiss what you say. Between crying wolf! and moderating everything into meaningless bland bureaucratese there's a sensible middle ground where you present the problem and its solutions in a reasonable and fair manner.

It may overstate the problem in economic terms, but may understate the problems connected with peak oil (and peak gas). It are the diminishing oil-exports (because of geology, problably starting the next decade)in combination with lower EROEI that will cause a lot of problems. You are right that 'crying wolf' closes most people ears, but at the same time there is a reason for panic because the governments will wait too long as they believe EIA, CERA, etc who don't see declining oilproduction before 2030 or so. If oilproduction declines with a few procent/year, oil-exports will drop faster mainly because of ELM.

The current model of the national energy grid is designed for maximum consumption. The model of the national energy grid is not sustainable for a national climate change strategy. We already see the repeating of past mistakes of investments by picking pet projects and having power carried across long distances with geothermal in Queensland. The current business practices of the national grid stakeholders will easily want to make the existing systems more efficient and effective when government policy has designed the system to maximise energy output.
Coupled with these problems of the national energy grid of high levels of distribution inefficiencies is how Renewable Energy Certificates (RECs) and Green Power both of which seemed to be designed for large economic players to benefit from. With Green Power it is lot clear what it is purchases and for RECs how it is counted.
Another level of complexity there seems to be little interest in a distributed energy system from the managers of the energy industry. Added to this is the executive management culture of the Australian power industry that is based on status quo management where the game is to maximise their sunk costs and their myopic strategic thinking.
Hence we do not see much roll out of Renewable Energy like large-scale wind farms.

http://www.scu.edu.au/staffdirectory/person_detail.php?person_id=13328

Michael,
"Hence we do not see much roll out of Renewable Energy like large-scale wind farms."

Not true, how about the 680MW of installed capacity in 2008(60% growth rate), and just a few days ago the Silverton Wind Farm near Broken Hill, 500MW capacity.
Infigen(IFN) is also completing 140 MW near Canberra due to be opened late 2009. About 550MW under construction before the Silverton project.
http://www.renewableenergyworld.com/rea/news/article/2009/06/planning-ap...

That's a substantial roll out of wind farms in my opinion.

minor typo:
"simple not possible" >> simply not possible

There's an unstated assumption in the figures for nuclear that I would call everyone's attention to:

Coal Oil(inc all liquids) Gas Uranium
Unit Billion Tonnes Billion Barrels Trillion M3 ThousandTonnes
Base Year 2007 2007 2007 2007
Resource 847 1,238 177 5,469
Consumption 6.4 27 2.3 65
Growth Rate 2.95% 1.39% 2.1% 1.2%
Life Expected 63 years 32 years 41 years 59 years
Resource Exhausted 2070 2039 2048 2066

Fission of 1 tonne of metal yields approximately 1 GW-year of electric power (depending on the thermal efficiency of the rest of the system).  Actual fission of 65,000 tons/year of uranium would indicate a nuclear electric power production of roughly 65 TW, give or take.

Obviously, actual nuclear electric generation is a tiny fraction of this figure.  This shows that the above figures assume (but do not state) a once-through cycle in thermal-neutron reactors.  Fast breeder reactors could increase the available energy by a factor of roughly 100.  (The resource figures may also assume no increase in the price of uranium, which is only a small part of the total price of nuclear power.  The price of uranium could increase tenfold and not increase the cost of power noticeably.  This would obviously increase the amount available.)

Last, thorium is not listed as a resource.  Thorium-232 is 100% convertible to U-233, which is fissile (only 0.7% of natural uranium is fissile).  Also, thorium is about 4x as abundant as uranium.  The addition of thorium to the nuclear energy base increases the total energy supply by a factor of roughly 400 over the once-through thermal-neutron uranium cycle.

Engineer poet
You are correct the assumption is based on current conventional once through light water reactors.

I agree, thorium breeder reactors present a means to significantly increase generation capacity and fossil fuel resource life. They were not included because they currently do not exist as an option. They will almost certainly be part of the energy mix when we are through with coal, oil and gas.

The purpose of this analysis was to highlight the need for some serious consideration of these energy alternatives that will bridge the time gap between fossil fuel exhaustion and a fully renewable energy based economy. Realistically, if we started on a thorium breeder reactor program today (I believe India has commenced some work) it will be 15 years before the first full scale reactor is operational and 30 years before they are being commissioned in sufficient quantities to have a mitigating effect on the problem we are trying to address.

phoenix,
There are reactors operating now as breeders and some designs such as Candu reactors can use thorium/U238 not as a breeder but to stretch out U235 fuel. They don't have to be operating now, we have lots of uranium available, even at today's relatively low prices. When prices rise to $300-500/Kg then breeders and thorium reactors will make more sense.
Here is a link to Barry Brook's post on the topic

http://bravenewclimate.com/2009/04/30/rethinking-nuclear-power/#more-1316

The other consideration is China's plans for nuclear are fairly ambitious at least after 2015 assuming the present 25 or so reactors planned or under construction are completed on time and on budget.

There's a small company called Thorium Power who are pushing a nuclear rod design that uses Thorium and can be inserted in existing reactors if 'm reading their marketing schpeel correctly... Sounds like a possible stop-gap...

I don't think we have scratched the surface of what can or will be done yet -nuclear is going to be a big chunk of the solution IMO because:

1. It is a base-load technology
2. It is scaleable to the sorts of power levels we need
3. It was the solution we went for before, France has proved it can work and BIG GOVERNMENT can control it.

On the negative side its an electrical solution and it has -shall we say- "an image issue"...

Nick.

"On the negative side its an electrical solution and it has -shall we say- "an image issue"..."

It does indeed. Today, nuclear proponents here and elsewhere are saying that it is perfectly safe and will be essentially free (especially given the scientific breakthroughs that are "right around the corner") and will not be targets of terror or sources of material for nuclear weapons.

It seems to me that I have heard this before from the same industry. How many times should we fall for this? You nuke proponents certainly have your work cut out for you.

All it will take is one serious breakdown and that is the end of the nuclear industry. One terrorist bombing, one shipment of fuel diverted to a 'rogue state' one core containment 'event'.

The costs associated with building conventional, light water plants cannot be wished away. Added to this is the uncertainty over liability. For some strange reason, the US tolerates + 40,000 fatalities on the highway every year. The same public will not tolerate less than fail safe performance of reactors.

Until the liability issues are resolved it is hard to see any public embrace of nuclear power. Some of the new designs show a great deal of promise, but these must be tested and assurance given that this inherent safety isn't compromised by scaling of plant production.

These are all stupendously expensive plants, who will pay, both for the plants themselves as well as cover the all important liability? The government is heading toward insolvency. The ratepayers won't shoulder the cost and allow themselves to be stuck with liabilities at the same time.

This is a concept killer. It put Shoreham in Long Island out of business. It is the reason no new nuclear plants have been built in the US since Three Mile Island. Electric utilities sell convenience. Selling anything else is difficult ... unless the power industry can figure out how to put nuclear power stations into the backs of peoples' cars.

On the other hand, strong opinions will soften when the beer gets warm and the television goes off.

All it will take is one serious breakdown and that is the end of the nuclear industry. One terrorist bombing, one shipment of fuel diverted to a 'rogue state' one core containment 'event'.

You think so?

  • One terrorist bombing outside a plant boundary would do roughly nothing.  Nuclear plants are very hard targets.  A bombing of a dry-cask fuel storage facility would scatter some stuff around and require folks to do some work with gamma cameras and whisk brooms.  This will probably be on the level of a chemical spill, minus the threat of seepage.
  • PWR fuel is enriched to about 3.5% U-235.  It's useless for bombs without a lot more enrichment, and diverting it would be a big waving red flag.  Proliferators will start with yellowcake, like Iran.  Spent fuel is also useless for bombs; the Pu isotope mix is way wrong.
  • We already had a core containment "event" in the USA.  Despite massive errors on the part of the operators, nobody was hurt; not even the pressure vessel was damaged.  Today's systems are even better.

I didn't mean to make this whole thread about nuclear, but we really do need to separate the facts from the propaganda.

Gotta admit, though. The whole thing keeps lots of lawyers rich, and politicians are almost always lawyers...

For some strange reason, the US tolerates + 40,000 fatalities on the highway every year. The same public will not tolerate less than fail safe performance of reactors.

Who knows? Maybe because cars and trucks are quite practical and nuclear power plants are actually not the only option to generate energy for a hot coffee or a warm shower or some lighting.

It is the reason no new nuclear plants have been built in the US since Three Mile Island.

So if the huge capital costs were not to blame, why did they have to pass laws forcing consumers to pay for the capital costs of new nuclear power plants in advance?
http://www.npr.org/templates/story/story.php?storyId=89169837

I agree, thorium breeder reactors present a means to significantly increase generation capacity and fossil fuel resource life. They were not included because they currently do not exist as an option.

They don't exist as a commercial offering, but thorium/U-233 has been tested as a fuel both in a light-water reactor (Shippingport) and a molten-salt reactor (the final run of the MSRE).  The MSRE already proved out the metallurgy, chemistry and neutron economy needed to verify the concept, so the next step could be commercial-scale even after 40 years of no work.

MSRs lend themselves to rapid construction (the MSRE was built in 4 years), so a large-scale deployment starting in 2015 is far from impossible.

Fission of 1 tonne of metal yields approximately 1 GW-year of electric power (depending on the thermal efficiency of the rest of the system). Actual fission of 65,000 tons/year of uranium would indicate a nuclear electric power production of roughly 65 TW, give or take.

Currently fission of 1 tonne of uranium yields 0.0045 GW-year of electric power:
Total nuclear electricity production 2006 worldwide:
2,658,000 GWh
Total uranium demand worldwide:
67,000 tons
http://www.cfr.org/publication/14705/global_uranium_supply_and_demand.html
= 0.0045 GW-year

The resource figures may also assume no increase in the price of uranium, which is only a small part of the total price of nuclear power. The price of uranium could increase tenfold and not increase the cost of power noticeably.

This is not the case with nuclear reactors commercially available now:
stockinterview.com/News/06082007/nuclear-fuel-conference-uranium-price.html
Dr. Kim opened our eyes.
He told his audience that fuel is four to five times the ‘hyped’ cost of nuclear power – between 20 and 25 percent instead of the mere five percent.
He announced, “At $1000/pound for uranium, a nuclear utility’s fuel cost would rise to $70/MWH compared to $5/MWH at legacy contract prices of about $20/pound.
Dr. Kim shot down the premature conclusion that utilities would rather pay the high prices instead of going through a costly decommissioning process. He said, “There is no compulsion to immediately decommission – stations can be held in standby or cold shutdown.”
Finally, he took up the matter of ‘utilities not caring about fuel costs.’ He pointed out, “Take $900 million from your company’s annual net profits. See how happy your management is.”
Because of what we've previously been led to believe, we questioned his numbers and conclusions. So we asked TradeTech’s Gene Clark for a second opinion. Clark emailed back and confirmed Dr. Kim’s calculations were accurate, writing, “At $1000/lb U3O8, I get $86.6/MWh total, but $16.6 is the carrying cost. Without the carrying cost, it’s exactly $70.”

Fast breeder reactors could increase the available energy by a factor of roughly 100.

Besides that fast breeder reactors are not commercially available (even though they have been working on them for decades), it's doubtful that they can compete with the capital costs and building speed of renewable and efficiency options which are available NOW and do not need to buy any fuel at all.

Phoenix and Aeldric,
I appreciate the efforts you have made in these posts.
I have some constructive criticisms/comments:

It's completely unrealistic to not assume that nuclear will play a significant role in electricity production using a mix of generation II and III reactors and breeder reactors using both uranium and thorium. Present known reserves will last X100 your estimates.
I would suggest at least 10% of the 198EJ of electricity should be from nuclear.

Secondly you seem to be over-estimating steel production or energy use, since today's steel uses less than 1Billion tonnes coal, less than 25EJ. This includes very high consumption from China with almost no recycling in China. In 40 years the one child policy will mean a lot of recycled steel and a lower steel demand. For example the US now recycles 78% of steel. So even if steel production increases 300% a lot will be from recycled, and direct reduction using electricity will use a lot less energy( you are not heating 2 tonnes air and coal /tonne iron ore). Even less energy if biomass is used for reduction in electric arc furnaces.

You are using equal amounts of wind and solar although wind is cheaper per kWh delivered. Presently wind is X 5 solar, either solar costs will reduce below wind, hence lower overall costs or wind will be at least X2-X5 solar. Either results in lower costs.

Your 25% capacity factor is only appropriate to N Europe( excluding Scotland which is >30% some farms 40-50%). Off-shore capacity factors are higher and in US average is 35% capacity factor for wind. I would suggest 33% a better world figure.
As more remote sites( better wind) are connected to grid capacity factor will increase. You can see this in UK, first farms in England(lower capacity) now a lot more in better wind locations in Scotland and off-shore islands.( see BWEA.com )Improvements in turbine design are increasing capacity 0.5% per year.

Demand for copper assuming 60% of the electricity comes from wind(20,000GW capacity) would require 20million tonnes of copper, while present copper reserves are 550 million tonnes with another 500Million reserve base. Similarly Nickel would be 1-2 tonnes/MW(20-40Million). Very large reserves of laterite ores exist in tropics as well as low grade sulphide ores. Both can be extracted by low energy cost acid leaching.

The major component of wind turbines is steel, 20,000GW would require 2Billion tonnes ( less than 2 years world production or 5% over 40 years, or less if you are assuming steel production will increase X3 fold)

There's a billion tons of copper in the Santa Rita mine. One mine. Whether it is economical remains to be seen but someone wants to give it a go.

A billion tons of copper or ore? Usually copper reserves are quoted in billions of pounds.

http://www.rosemontcopper.com/PlanOfOperations.asp

Proven and probable reserves of half a billion tons. They don't seem to be planning to get it all out of the ground, but they can change their minds based on the price of copper. This mine will (if allowed) produce 10% of this nation's copper which is second only to Chile.

robert2734,
I think you have made a mistake, counting tonnes of ore, not tonnes of copper at 0.2% of ore. Mine reports are a bit confusing. Just the same this mine could make a significant contribution to that 20million tonnes over 40 years.

110,000 tons/year all by itself. There's copper propyrite deposits like this all over Arizona.

This is a really great post, thanks Neil! I love seeing comments which actually work to mutually iterate towards better understandings!

This is very interesting stuff!

Neil
See above comment regarding nuclear.

Not so sure about your conclusions concerning steel production. In 2050 china may not be the world boom economy but we could be seeing the Africa boom. I see your point concerning the higher proportion of recycling in developed economies. However, as they still only represent a small proportion of the world population I think it is reasonable to assume that growth of raw steel manufacture will approximate GDP growth for some time to come. Again, this is based on the assumption of a BAU model.

I think you may have missed the point with respect to the comment on higher energy costs associated with resource extraction. We did not make this comment in respect of only the imbedded energy cost in power generation plant. It was intended to refer to the economy as a whole. Some research has been undertaken and reported in TOD on the effects of EROEI on oil extraction. Exactly the same effect will apply to all resource extraction industries. As they approach depletion the energy cost associated with their exploration, mining and refining will grow and this growth will have a exponential element to it. I don't know the degree to which this aspect will impact future energy demand but it needs to be identified as a factor for consideration.

I take your point on the energy mix. If solar PV does not achieve significantly better than the stated $5000/kW then it is unlikely that it will constitute the stated 10%.

WRT the capacity factor there are a number of reasons that I took the relatively pessimistic view on this. The main one that most people overlook is the implication of having a large proportion of the generation capacity "uncontrollable". In the mix I have nominated there is 60% of the capacity that would come under this category. The high capacity factors currently being displayed by wind farms are only achievable because they are feeding into grids being buffered by easily controllable coal and gas fired plant. As an example I will use the numbers for the Australian grid because I know them. The generation is made up by 90% coal and gas fired generation (with a little hydro and wind). The coal and gas fired plant has a reliability factor in excess of 96%. Despite this the system as a whole only achieves a capacity factor of 56%. In a future configuration with no coal and gas the buffer will be supplied via hydro, biomass and geothermal. However you will be trying to get 40% of the energy mix to fill in for the unreliable 60%. In order to provide the reliability of supply you will need to build more reserve capacity from all sources and hence the capacity factor will be lower.

phoenix,
You would be correct about steel if Africa became another China, that's fairly optimistic. If we are still considering using lots of coal and oil by 2050 than declining EROEI would be an issue, but I thought we are assuming they are essentially finished or minor energy resources(<10% of present consumption).

The case for needing more energy for mineral extraction is less clear, because of the big advances in extraction technology. Many improvements are still possible including various chloride electrochemical leach methods(Halex process by Intec.com.au), Chlorox process, acid and bacterial leach methods that reduce mining costs and allow low grade ores to be extracted.

The low capacity factor of NG is due to the high cost of fuel and the high peak prices, lower capacity factors give higher returns. With wind its due to the variability of the energy resource, and influences the cost of power, lower capacity factors give lower returns. With CSP solar however with very minimal storage, it can match peak demand so is not a problem.
With wind the only solution is a very large grid to even out supply and pumped hydro or other hydro. IF Hydro accounts for 15% of electricity it could accommodate a much larger amount of wind energy at least 60%, by reducing the hydro capacity factor, a very inexpensive task since most of the cost of hydro is the dams not the turbines. This is how hydro is presently used in China and Australia.

With wind the only solution is a very large grid to even out supply and pumped hydro or other hydro.

Neil, I think that wording is a bit too strong. Demand Side Management (DSM) is very effective, and very cheap.

The US has 220M light vehicles. Imagine 220M EVs, able to absorb wind output peaks on a daily basis, and supply the occasional burst of power. They could increase night time demand, which would reduce the need for expensive solar, and eliminate the single largest problem for both wind and nuclear. Incidentally, it would also eliminate diurnal variance/intermittency as a problem.

220M EVs, each able to absorb an average of 2 KW for 24 hours: that's 440GW, or the average daily US grid output. They could absorb peaks of 1.1 TW quite easily: that's only 5KW per vehicle, or a 220V 25A charging circuit. Very occasionally, they could also do the reverse: power the entire grid for 24 hours, or supply a shortage of 25% for up to 4 days.

All of this, essentially free to the grid, as users would pay for the EV for their own transportation needs.

Now, expanded long-distance transmission is certainly a good idea - we just don't need to go overboard.

Realistically, you could use wind for 50% of the grid, solar for 20%, nuclear/wave/geothermal for 20%, and biomass for the 10% of balancing that would be needed for the occasional multi-day lull in renewable output.

That would give you a much cheaper grid than envisioned in the Original Post.

Nick,
While EV's will provide a sink during periods of high wind, the problem will be low wind conditions during the day for relatively small regions. A smart grid will be able to reduce some demand, and solar will provide some of the peak, but that still leaves a big gap of at least 40% expected demand(with 50% wind). V2G is unlikely to be able to supply more than a small part of this. While NG is available that's going to be the cheapest option, and for this reason a small amount of NG should be saved for this purpose since we already have lots of NG peaking plants.
Post NG, 15% hydro ( or even less) could be used to fill the shortage in one region lasting perhaps a few hours to a few days. This would require either more pumped storage or existing hydro to have about 3 times the turbine capacity as average production. In the US and Australia its about x2.5 presently. A long range grid will ensure that some of this load can be shared with other more distant hydro and wind farms that are operating. If only 5% hydro is available, it would need X8 the turbine capacity.

Ahhh
Wouldn't the easier solution be, to install an overcapacity of wind and accept the implied lower capacity factor.

Undoubtedly that will be part of the solution, just as today the US has 1,050GW in capacity, but only 440GW of average demand.

OTOH, that would probably be the most expensive solution, if used as a primary solution, and especially in those areas where wind has a low capacity factor at peak. I expect that we'll have mix of things: long-distance transmission (just like now, but somewhat larger); DSM (aka smart grid); central utility storage (including pumped storage, as we've had for many decades, and battery (including conventional and flow) as a few utilities are now installing); synergy with solar; backup by biomass and FF plant; other things we haven't thought of, or that aren't practical yet but will probably get there, like central hydrogen fuel cells or solid fuel cells.

A mix of things is by far the cheapest. Analyses of single solutions are helpful as boundary values (i.e., we see the worst case scenario), but are far more expensive than a good mix.

And, finally, DMS is by far the cheapest and most effective solution, and it's badly underutilized. Utilities don't have the regulatory or incentive structure to use DSM now. They're incented to build capacity.

As an example of perverse incentives, look at the vast majority of thermal generation plants in the US now, and compare them to where we were when we started. The first plants, built by Edison, used co-generation. Many of them still exist in NYC. Now, because utilities are regulated monopolies, co-gen is very rare. This is very inefficient, but there you are.

Similarly, we have these later afternoon A/C peaks, because residential customers pay a flat price regardless of time of day, and utilities are paid to build generation (because they're given a flat ROI on generation). This is completely artificial.

We have all the generation we'll need for quite some time, if we change the perverse regulatory incentives. If we do so, we can completely stop construction of new FF plant, and settle down to the task of replacing FF with wind.

V2G is unlikely to be able to supply more than a small part of this.

Why do you feel this way? Is there any question that in 40 years that most of our vehicles will be PHEVs, if not EVs? Is there any question that batteries will improve dramatically during that period, given the explosion of innovation we see now? I've noticed at least 5 major companies, like Toshiba, LG, etc who have their own 2nd generation Li-ion chemistries in or close to production. Most of these have extremely long lives, such that EV/PHEV batteries are highly likely in a few decades to last the life of the car. In that scenario, V2G becomes cheap and practical.

Imagine 220M EVs, putting out 2KW each, and providing 440GW (the average US grid output). Or, 110M EVs, putting out 4KW each, and providing 440GW (the average grid output).

Nick,
While V2G is a great concept, and can play a very significant role in short term management, there are problems on relying upon V2G for major wind back-up. The issues are back-up is needed during the day, when a large number of EV will not be available, because they are not at home charging stations or will not want to be discharged in late afternoon because a full battery is desirable for the home trip. At least for PHEV once in a while this would be OK, but if it's used most afternoons the owner is going to use more expensive gasoline.
The total capacity of even 220 Million vehicles say giving up 2kWh is 440 GWh only 30 mins of peak demand. The US and Canada have together 150GW of hydro capacity that could be expanded to 440GW and run for days at that power output.

You cannot compare low capacity of NG with wind because operating wind is zero cost, operating NG is most of the cost. It's better to always use nuclear and wind power, by displacing NG or by using for pumped storage or EV charging.

I see V2G as valuable for vehicles at a home base for the day where they could sell perhaps 4kWh of power(perhaps one third of vehicles), but the big role for EV is taking up that extra wind capacity when demand is low( eg during night) when 95% of vehicles will be plugged in at home base. If we have an acute oil shortage we won't be wanting PHEV's to be using gasoline unless absolutely necessary, NG is likely to be more plentiful and used as now for peak demand.

back-up is needed during the day, when a large number of EV will not be available

Neil,

You need to have an intuitive feeling for just how underutilized the average light duty vehicle (LDV)is.

The average US LDV drives less than 12,000 Vehicle Miles Traveled (VMT) per year. Assuming an average speed of 30 miles per hour, that's only 400 hours per year, or 5% of the time. Peak utilization is during commuting rush hour, but probably only about 15% of vehicles are in use at that time (45% of VMT is for commuting. if 75% of commuting happens between 8-9 and 5-6 Monday - Friday, then 4,000 miles over 1040 hours at 30 MPH is about 15% utilization). European and Australian numbers are about 40% lower!

because they are not at home charging stations

It won't be a very large infrastructure investment to put connections in parking garages and parking meters. Most of the infrastructure exists already - it's the final few feet that's needed. It could build out very gradually, and is likely to do so regardless of V2G.

or will not want to be discharged in late afternoon because a full battery is desirable for the home trip

A 50KWH PHEV/EV only needs an average of 3 KWH to get home.

if it's used most afternoons the owner is going to use more expensive gasoline.

This would be rare. LDV generated electricity would only cost at most about $.50 per KWH (based on $150 bbl & 10KWH generated per gallon). In those rare cases, that last bit of capacity would be quite valuable to the grid, and would be far cheaper than having a lot of generating capacity lying about waiting to be used 1% of the time.

The total capacity of even 220 Million vehicles say giving up 2kWh is 440 GWh only 30 mins of peak demand.

In the US, peak demand is only about 650GW, so that's 2/3 of all peak demand. 220M vehicles, each with 50KWH of capacity, could keep that up for 25 hours, or provide 660GW for 16 hours.

The US and Canada have together 150GW of hydro capacity that could be expanded to 440GW

That sounds great, but even Alan Drake hasn't suggested we could do so much. Could you provide more info?

I agree that DSM (with and without EV/PHEVs), long-distance balancing, hydro, NG and central storage (pumped and battery) will also be very, very helpful. We have a lot of tools at our disposal. I just want to demonstrate the power and cost-effectiveness of V2G.

A smart grid will be able to reduce some demand, and solar will provide some of the peak, but that still leaves a big gap of at least 40% expected demand(with 50% wind)

Have you considered the fact the fossil fuels currently needed for heating and cooling purposes also have to be substituted by efficient heat pumps which leads to a higher electricity demand (more installed capacity) and their heat energy can easily and cheaply be stored (the capacity factor has little relevance)?
(A windturbine with a maximum capacity of 3 MW has a significantly higher capacity factor at 0.5 MW than at 3 MW. And heat pumps only run at 3 MW output and never at 0.5 MW. In Switzerland heat pumps have been remotely controlled (utilities send a signal) for over 20 years because there is excess electricity at night.)

Can we have a breakdown on what you need 20 million tons of copper for? You do know that high voltage power lines are aluminum clad steel for strength to weight ratio. My house is wired with aluminum. An electric motor/generator is the last place I'd want to substitute a higher resistance material but I assume there's one generator per wind turbine.

robert,
Wind generators have about 1tonne copper/neodymium per MW capacity. Fully recyclable but non the less need a lot of turbines.

http://enclim.mensch.org/enclim.cgi/GlobalCalming

One gram of copper per watt is one metric ton of copper per MW. Yep, I'm convinced. Good job Neil. The website I reference is too "peak copper" to be credible but they cite Vestas for this number so I believe it.

A windfarm also has miles of copper wire for grounding and lightning protection so this may be an underestimate, perhaps a serious one.

robert,
The Vestas V90( 3MW) only has 1.5 tonnes copper(0.5Tonnes/MW) but some gearless turbines have about 1.5Tonnes/MW.

The other issue is Neodymium a so called "rare earth". These rare earths are as abundant as copper and zinc, but not found in very concentrated ores. They also are difficult to separate from each other, but now there are good ion exchange resins. If the price rises a little( only a 100Kg/MW is required ) should be lots of low grade deposits that can be mined.

As you said, can use Aluminum in place of copper for lightning protection etc.

It's worrying when you see statements along the lines of 'algal biodiesel has to work'. US Energy Secretary Chu seems to be saying 'CCS has to work'. What if they don't?

Hydrogen from 4th generation nuclear could solve a lot of problems. It could reduce iron ore or upgrade low net energy biofuels. I agree we have to put everything on the table like it or not. It may come down to 4th gen nukes vs dieoff.

t's worrying when you see statements along the lines of 'algal biodiesel has to work'. US Energy Secretary Chu seems to be saying 'CCS has to work'. What if they don't?

Excessive faith in technology and Human Ingenuity has got us this far, it has to push us past these problems! :p

I agree we have to put everything on the table like it or not.

Actually, the correct answer for a modern free market society is always:
We have to invest in anything that generates a high-benefit/costs ratio and a high-benefit/building-time ratio.

Hydrogen from 4th generation nuclear could solve a lot of problems.

Since capacity factor is irrelevant in hydrogen production, what's the reason that wind power, which as opposed to the nuclear generation IV is available NOW, should not be used to produce hydrogen?

It is a bit of a nitpick, but thermal storage with solar thermal might decrease overall cost. The basic assumptions are
total cost = C + S + T
Where: C is the cost of the collectors (pipes plus mirrors)
S is the cost of thermal storage.
T is the cost of the turbomachinery and power conditioning.
Clearly; C scales linearly with planned annual output (J/year)
S probably scales with the thermal storage capacity.
T scales with the nameplate capacity.
The idea is to overbuild the collectors, i.e. the turbines are underpowered wrt. the capacity of the collectors, the excess is stored. Then the turbines can continue to run into the night. If the turbines are a significant fraction of the overall cost, then overbuilding the collectors, and adding sufficient thermal storage can cut the cost per joule. In any case, this price optimization is not likely to be a huge factor, but at least it provides an avenue for reducing overall cost while simultaneously smoothing at the supply temporal variations.

Since no one has done any ad hominens, I'll start: "Nanny nanny boo-bo"!

" * Reduction in energy demand through conservation
* reduction in energy demand growth through population limitation/reduction
* continuing the limited access to energy to large portions of the world population

* breakthroughs in energy conversion efficiency
* large new resource identification
* the roll out of renewable energy generation raised to a war footing for all industrialised countries"

I noticed that the last three of these are essentially wishful thinking.

I also noticed that it hasn't taken long for the nuke enthusiasts to come out of the woodwork. So let's again reiterate:
--too dangerous in a world characterized by a global war on terrorism
--too expensive in a world in the throws of The Greater Depression
--too hazardous to current residents near mines, near roadways carrying fuel and waste, near plants...
--too hazardous to posterity
.
.
.

The first, second, third....Nth priority has to be "reduction in demand."

Education, taxes, rationing, anti-consumption ads, curtailment of consumption, intentional recessions and depressions, aggressive and effective population control starting with the biggest consumers, end to corporate (super-) person-hood...Total and rapid powerdown at all levels.

These, rather than focusing on technofixes, are the necessary approaches we have to carefully consider then rapidly implement.

What weight do you give to the inevitability of nuclear war?
I weight it at about 80% due to the death throws of the old economy.
Get depressed if you feel the need, but we have to prepare for this greater than zero possibility.
If they are not survivable then there is no problem.
But if they are survivable then we have a moral resposibility to prepare.
I argue that the implementation of nuclear power will reduce the likelyhood of a nuclear war by making the transition a weeny bit more controlable. The slope down will be less steep with nuclear power.

Great. Then let's help Iran and North Korea with their nuclear program.

Are they the bad guys? I thaught it was the Germans.
I must try to keep up with current fads.

If you think nuclear is too dangerous, you need to look at LeBlanc's LFTR presentation, especially the part about denatured-salt reactors.  The fuel in a denatured reactor would be well below bomb grade, requiring isotope separation to upgrade.  This is harder than upgrading natural U because of the U-232 and U-234.  You don't have to make it impossible to turn into bombs, just more difficult than starting from natural U.  These reactors could be safely supplied to almost anyone for carbon-free power.

If we are only concerned about the industrialized world (which already has bombs and nukes), we don't have to worry about proliferation and can build whatever works.

"If we are only concerned about the industrialized world (which already has bombs and nukes), we don't have to worry about proliferation and can build whatever works."

I'm sure such an approach will further endear us to the rest of the world. Not.

We need some very strong regulations with from the government with regards to energy saving. How come a mobile phone can stay online using 0.5 W and we get a settop box using 24W "for free"?

Simple engineering should be able to reduce this for very small money.

Energy is to cheap. What will happen if energy in the developed world will double in price? Rapid demand destruction. The settop box now costs (in the Netherlands) EUR 48/year for energy and nobody cares. Double it and people may care...

In the Netherlands private households could reduce their energy consumption (electricity) by half without reduction in quality of life.

First, an excellent article. My few nits are essentially opinion.

1) I agree with above post, that solar-thermal-with-thermal-storage has greater potential than offered. Serious unit cost reductions will be achieved by volume installation and advancing technology. NREL / Sargent and Lundy's engineering paper proposes wholesale electricity out costing between $0.035 and $0.062 / kwh after the first 8 GW are built.

2) I think solar PV will cost a LOT less than $5,000 / kw once a market the size proposed is formed. eg. Optical Rectenna has been proven at laboratory level, awaits advancements in nano-scale diode fabrication which can be assumed definite within this time frame.

3) Some of the newer wind generation technologies should be capable of significantly reducing those costs / kwhr out, and possibly percent availability eg. IF WindJet's new turbine proves real, they're discussing useful generation with winds from 1 kmph to 100 kmph at 4x power density per unit land area.

4) On the time scale of 40 to 50 years, it can be taken as certain that SOME novelties we don't yet even envision will crop up. That could be Lighter-than-Air wind generators floating in the jetstream, ocean current generators, ocean differential density exploiters, etc.

5) TOU metering + realtime pricing COULD seriously help to enable intermittent generation, eg. by STRONGLY ENCOURAGING / incentivizing optional useages such as PHEV charging, air conditioning with ice storage, etc. etc. to happen only when the wind is blowing and / or the sun is shining. Needs overspec grids, but that can be handled as well by incentivising load levelling the same way. Mainly needs long-term vision and planning.

Overall though, your articles do an excellent job of laying out the scale of the real issues as accurately as can be done from a scientific / egineering perspective. Kudos. Hopefully in your next, you can address the REAL problem, which is "We know it CAN be done, but WILL it be done? What obstacles there?". I'm guessing that the time frame available is somewhere within the period of exhaustion of Natural Gas resources in each of the major markets, N America, EurAsia, M East and Africa and India, S. America. To my knowledge, N America has only about enough gas (including tight excluding clathrates) to last at present rates of consumption about 40 yrs. Assume LNG can bridge Latin america that far as well. That means that we need to be AT LEAST well into this plan before 2050, and better would be to have completed it by then so we can keep some fossil fuels for other uses for posterity. Will incumbent suppliers allow ANY transition to start before ALL N. Gas is gone? I remain sceptical.

Too much negativity.

Australia's electricity consumption = 1 quad = 300 Twh
Assume 50% electricity from hydrogen storage (150 Twh used in the daytime) and the efficiency of hydrogen is 25% per Ulf Bossel so 600 Twh in hydrogen storage.

Australia's oil consumption = 2 quads = 83 million tons of hydrogen.

It takes ~60 Mwh to make by electrolysis and compress a ton of hydrogen or 5000 Twh.

A 25 kwe Stirling Systems Suncatcher gets a daily 2 kwh/m2d or 730 kwh/m2a.
http://www.stirlingenergy.com/advantages.htm

5000 + 600 + 150 = 5750 Twh
5750 Twh/730 kwh/m2= 7.877 billion m2 or 7876 km2.

Area of Sydney Australia = 12058 km2

So cover the dear old outback with .6 Sydneys of Suncatchers and you're done.

You can thank me later.

I shall thank you now.
I had forgotten all about Stirling engines.
I bookmarked the page.

The infrastructure required for provision of biofuels will be a significant challenge, hence the limitation of this fuel source for all uses except where it is irreplaceable because of energy density. The production of biofuels on the scale required is unprecedented. Production of sugar or grain based ethanol for this volume could not be contemplated. It appears that the only viable biofuel at this level of production will be production of algal based biodiesel. Research has indicated that this form of biodiesel production will involve plant capital costs in the region of US$6.5 Million per megalitre of production capacity. The capital cost of the infrastructure to produce 5,800 GL per year will therefore be approximately US$37,900 Billion.

Whoops???

Let's go through this in detail.

$6.5 Million per megalitre of production capacity.

A megalitre is 1,000,000 liters, or about 5,400 barrels. I presume that we're talking about annual production capacity, so a "megalitre of production capacity", would produce about 54,000 barrels over 10 years (a conservatively long pay-back/capitalization period).

So, we're talking $120 per barrel before any operating or maintenance costs - these would bring it up to at least $150 per barrel.

Why would anyone pay that much? Long-haul trucking would be entirely replaced by rail at that price. Water shipping would go to batteries and fuel cells. Personal transportation would go to EVs (and some PHEVs that used liquid fuels for perhaps 5% of their motive power). All that's left is air transportation.

5,800 GL per year? That's 32M barrels per year! I think we'd probably use less than 5M barrels per year at that price.

Does anyone suggest that in 50 years we'll have less than 20M of liquid fuels from remaining conventional crude, NGLs, tar sands and biofuels? They'll all be far less expensive.

Asside from which everyone needs to have it drummed in, "photosynthesis is THE LEAST efficient method of converting solar energy into a form which society can use". 1% to 2% efficient in perfect tropical conditions with perennial sugar cane, > 1/4% net efficient in temperate seasonal climates. A set of solar-thermal collectors (or even 16% efficient PV) simply out-performa ANY means of photosynthesys, period, in every way. Include everything, input materials, transmission, storage, etc.

I agree. A small quibble: bio-mass for burning (for space heating or for electrical generation) is pretty cheap. It may not have a high theoretical efficiency, and it may not be enormously scalable, but it's still pretty useful.

•Although the cost has been based on a range of assumptions concerning energy technologies, it is unlikely that a different mix of conversions or replacement technologies would greatly affect the bottom line price.

Moving to a mix of, say, 50% wind, 10% nuclear/wave/geothermal, 20% CSP solar and 20% biomass wouldn't affect the costs?? Wouldn't it cut it by almost half?

•The figure quoted only represents the major energy production plant required. In parallel with this will be a similar cost associated with the changes made by energy users (i.e. electric vehicles, mining and manufacturing equipment, rail lines, power transmission, metal smelters etc. etc....)

Not over 50 years. The costs would be negligible, as things were replaced as needed. The costs would come from replacing things before replacement was needed, which would only come from a much faster deployment. Incidentally, I would strongly advocate a much faster deployment to deal with CO2, but that's different.

•The cost assumes a single transition from the current energy production infrastructure to the final renewable infrastructure. This won’t happen. As successive governments are driven by the need to maintain the power on and the fuel tanks full there will be a staged series of interim technologies implemented. Depending on the quality of vision of political and industry leaders these interim technologies could consume as much or more than the cost indicated for the final conversion.

No. Renewable electrity and efficiency are the best candidates, and just about everyone is clear on that.

Hydrogen is already on the way out. Nuclear is still being debated, but it will work just fine to the extent it's deployed. Algae is the only thing I can think of that might fit this description, and I can't imagine it will go anywhere if it can't prove itself. Other biofuels may cause quite a bit of environmental damage, but their direct costs won't be especially high. I can't imagine what you're thinking of.

Given the above considerations it is likely that the total costs associated with transitioning the world to the fully renewable economy will be in the order of US$ 150 Trillion.

The base figure for generation is way too high. The algae proposal is highly unrealistic. This final figure of roughly $50T is completely unsupported.

I appreciate you're giving this a try, but this is barely a pre-draft outline of an analysis.

I ask you to consider Australian experience with the World Solar Challenge, where I participated in 1996. Solar panels for these race cars have recently been downsized from 8 sq meters to 6 sq meters because they were going too fast!

If humanity can't figure out how to get away from the Internal combustion engine at ~20% efficiency and cars which weigh 2 tonnes to carry a single person, we should give up and go back to the 18th century. Considering that the goal is to move people, not metal, then that 20% * 100 kg / 2 tonne = 1%. It's almost as bad for trains and buses. This is no way to bungle into the future, and these models must incorporate better technology assumptions to overcome the absurdities that result from imagined direct oil substitutes.

The USA uses about 25 Quads = about 25 ExaJoules for transportation. Cutting that back to 5 Quads / Ej is feasible, and obviates the absurd notion of making a replacement fuel that perpetuates the automobile which is effectively 1% efficient, while also being responsible for ~ 1 million deaths per year (40,000 in the USA) plus countless injuries.

In California we are on course to build a pilot 100% solar powered non-linear personalized public transportation system that will pay for its energy source (solar PV) in 4 years without any subsidies. http://www.solarevolution.com/.

Macro analyses must incorporate dramatic reduction in energy usage resulting from disruptive technologies. We have done energy / climate / depletion models for certain countries using methods similar to yours and welcome the opportunity to compare notes. Yes it's going to cost money. But spending it, with due consideration of EROEI and other critical metrics, before BAU destroys our basic infrastructure, will save trillions.

Any combusted liquid (or gas) fuel in a personalized vehicle, though plausible in rural areas, is the worst possible BAU in the urban context.